2008 Timeline Chart for
Conversion Application |
|
Date |
Action |
Done |
|
11/9/07 |
Letters of intent received. |
ü |
|
11/11 |
Develop Empire Health Sale-general information Website. |
ü |
|
1/11/08 |
Applications received. |
ü |
|
1/12 |
Application screening began by Department of Health (DOH) and
Attorney Generals Office (AGO). |
ü |
|
1/14 |
Set-up weekly meetings with review team and AGO team– Ongoing. |
ü |
|
1/25 |
Independent valuation expert opinion contract- Statement of work
developed. |
ü |
|
3/3 |
Advertise and post Response For Proposal (RFP). |
ü |
|
3/5 |
Application screening
deadline. Letter identifying missing items in application. |
ü |
|
3/10 |
Release RFP. |
ü |
|
3/28 |
Receive contract proposals. |
ü |
|
3/31 |
Evaluate
contract proposals. |
ü |
|
4/1 |
Select contractor and prepare final contract materials. |
ü |
|
4/1 |
Empire Health Website refinement. |
ü |
|
4/3 |
File contract with Office of
Financial Management. |
ü |
|
4/18 |
Screening response submitted by
Community Health Systems (CHS). Revisions expected. |
ü |
|
4/22 |
Revised screening response submitted by
Community Health Systems (CHS). |
ü |
|
4/23 |
2nd application screening begins. |
ü |
|
5/8 |
Application sufficiently complete to
begin review |
ü |
|
5/8 |
AGO requests additional information |
ü |
|
5/12 |
“Beginning of Review” notification
published in the
Spokesman Review. |
ü |
|
5/29 |
Independent Evaluation /
Expert Opinion contract
signed |
ü |
|
6/3 |
Public Hearing Notices
Published in Spokesman
Review |
ü |
|
6/3 |
DOH Requests Additional Information |
ü |
|
6/6 |
Received Responses to AGO 5-8-08 Letter |
ü |
|
6/6 |
Received Responses to DOH 6-3-08 Letter |
ü |
|
6/16 |
Meeting with KPMG |
ü |
|
6/18 |
Meeting with KPMG |
ü |
|
6/20 |
KPMG Report Received (Summary) |
ü |
|
6/25-26 |
Public Hearings Scheduled:
Click for Details |
ü |
|
7/14 |
Close of Public Comment |
ü |
|
8/8 |
Attorney General (AAG)
Advisory Opinion Received |
ü |
|
8/20 |
Certificate of Need and Conversion decisions released |
ü |
|
8/27 |
Draft CHS/Empire Acceptance
Responses Received |
ü |
|
8/28 |
Conference Call with CHS, Empire,
and AGO -
Condition Acceptance Letters -
Empire Foundation -
CHS |
ü |
|
8/28 |
AAG Letter Received Regarding Fulfillment of certain
Conditions |
ü |
|
8/28 |
Empire Health Foundation (new Foundation) filed Articles of
Incorporation Received |
ü |
|
8/29 |
Certificates of Need issued for
Deaconess and
Valley hospitals and
final Conversion Approval for
Empire Foundation and CHS Released |
ü |
|
|